Unit Price in Public Procurement 2026
Unit price in public procurement: price per unit of quantity in the bill of quantities. Significance, calculation, and difference from lump-sum price in public contracts.
Definition: The unit price is the price offered in the bill of quantities or price sheet for a defined unit of quantity of a tendered work item, which, multiplied by the actual quantity performed, results in the total price for that item.
Last updated: January 2026 · Legal basis: VOB/B § 2, BVergG 2018, ÖNORM B 2110
What is the unit price?
The unit price is the basic pricing format for the award of construction works and often also for supply and service contracts where the exact quantity of the work to be performed is not yet definitively known at the time of the tender. In the bill of quantities (BoQ), the contracting authority sets out a description of the work and an estimated or expected quantity (preset value) for each work item. For each item, the bidder enters the unit price per unit of quantity (e.g. per hour, per square metre, per piece, per linear metre).
The total price of an item is calculated as: unit price × quantity = item amount
The sum of all item amounts gives the bid total.
Unit price vs. lump-sum price
The unit price contrasts with the lump-sum price, where a fixed price is agreed for the overall performance, regardless of the actual quantity performed.
| Feature | Unit price | Lump-sum price |
|---|---|---|
| Quantity fluctuations | Billed by actual quantity | Fixed price, no quantity adjustment |
| Planning risk | With the contracting authority | With the contractor |
| Use | Construction works, quantity-dependent works | Clearly defined overall works |
| Supplementary order for quantity increase | In principle billable | Only in case of substantial deviation |
Significance in public construction procurement
In the award of construction works under VOB (Germany) and ÖNORM B 2110 (Austria), the unit price is the dominant pricing format. Under § 2 VOB/B, remuneration is billed at unit prices unless a different agreement (lump-sum contract) has been concluded. If the actual quantity performed deviates by more than 10 % from the quantity provided for in the contract, a claim for price adjustment exists under § 2(3) VOB/B.
Calculation basis
Unit prices must include all costs necessary for performing the work, including labour costs, material costs, equipment costs, site overheads, general business overheads, and profit. A bidder who deliberately calculates individual unit prices speculatively low (speculative calculation) risks having their bid excluded due to non-viable prices.
Related terms
FAQ
What happens if the quantity actually performed deviates significantly from the estimate? For construction works under VOB/B, both contracting parties have a claim for price adjustment in the event of quantity deviations of more than 10 %. The details are governed by the contract and § 2(3) VOB/B.
Can a contracting authority reject unrealistically low unit prices? Yes. Contracting authorities are required to clarify abnormally low bids (§ 60 VgV). If it turns out that individual unit prices are calculated speculatively and the overall bid is not economically viable, the bid can be excluded.
Last updated: January 2026 All information provided without guarantee. For legally binding advice, please consult a law firm specialising in public procurement law.
Book a demo.
See what BOND finds for your company — tenders, suppliers, and partners you'd never discover on your own. Cancel any month, anytime.